Project Profile - Commercial solar installation in Haworth

UK REIT Solar & Battery Storage Project

AlphaGen Energy was appointed to design, procure and install a complete renewable energy solar and battery storage solution for a UK REIT distribution warehouse. The objective was clear: reduce electricity grid reliance, future-proof the energy supply and drive operational efficiency through long-term energy cost reduction.
UK REIT
Distribution Warehouse
UK
Lorem

PROJECT OVERVIEW

AlphaGen took this project from concept to completion with a clear, well-managed process. Design, approvals, installation and commissioning were delivered seamlessly, with quality evident throughout.

The solution strengthened energy resilience, reduced operational cost exposure and delivered long-term energy and asset benefits.

THREE-PHASE PROJECT DELIVERY
hand-drawn-line-green
data icon

Phase 1 – Data Capture & DNO

AlphaGen fully managed the DNO application process, incorporating grid feedback into the final system design to ensure compliance and seamless approval.

solar panel icon

Phase 2 – Strategic System Design

A future-ready renewable energy system was engineered to maximise on-site solar consumption, reduce peak demand exposure and support long-term resilience.

ems icon

Phase 3 – Implementation & Delivery

The project was delivered, fully tested and commissioned on schedule, with immediate operational impact from day one.

STRATEGIC SYSTEM DESIGN

What AlphaGen Delivered
  • 480 Trina Solar 495W Vertex S Panels

  • 4 x 50kW Hybrid Inverters with 61.44kWh Battery Stack

  • 4 x Sunsynk F60 External PowerHub BESS Units
    Fully fire-insulated, IP65-rated self-contained hubs – the first installed in the UK

  • Intelligent energy management system integration

The external BESS PowerHub solution simplified installation, freed internal space and supported insurance compliance.

Sunsynk Power Hub units in industrial settings

PROJECT PREPARATION

Complete system design

Following detailed site analysis, AlphaGen developed a complete system design aligned with the warehouse’s operational profile and energy demand.

Early DNO engagement ensured grid capacity was understood and managed effectively. All approvals, procurement and compliance were handled in-house to streamline delivery.

Installing Solar Panels at Twilight

PROJECT DELIVERY

Installation and commissioning were executed to the highest safety and performance standards.

Upon commissioning, the system immediately supplied 99% of the building’s energy requirement directly on-site. A high-performance battery system maximises solar self-consumption while reducing peak demand exposure.

An intelligent off-peak charging strategy further optimises cost through differential tariffs.

The system is future-ready, with the ability to export surplus energy to create a potential additional revenue stream.

SYSTEM FACTS

Open battery storage at dusk

Project Gallery

Make it Happen

PROJECT FUNDING

Flexible funding structures were explored to align capital deployment with asset performance and long-term return objectives, supporting institutional investment criteria.